LAKE MILLS AREA SCHOOL DISTIRCT

LONG RANGE FACILITIES PLAN

FEBRUARY 2016

 

2016-2017 School Year

Replace original air handling equipment, original boiler,

relocate fume hood and provide cooling for data closet at high school.                     $985,000

Scheduled maintenance.                                                                                             150,000

 

2017-2018 School Year

Replace high school roof-sections 3 and 10.                                                              $155,000

Scheduled maintenance.                                                                                              150,000

 

2018-2019 School Year

At the high school, construct an addition in the IMC wing to accommodate

general classrooms and remodel and upgrade the existing media center (library).   $5,500,000

Scheduled maintenance.                                                                                             150,000

 

2019-2020 School Year

Scheduled maintenance.                                                                                            $150,000

Additional high school maintenance.                                                                            100,000

 

2020-2021 School Year

Scheduled maintenance.                                                                                            $150,000

Additional high school maintenance.                                                                            100,000

Replace high school roof-sections 7 and 8.                                                                  TBD

Last Updated: 8/10/16